Sorry for not keeping you as up to date over the last couple of month on what has happened on the building front. After the house had been built in the middle of December, not much happened over Christmas and in January due to the weather. Below are some pictures of what happened since than.
- As you might remember from the building, there was no garage door yet. This was placed end January.
- In the beginning of February the electricians entered the house and installed electrical, tv and networking cabling.
- Inside canalization and some parts for toilets where installed end February and beginning of March by a group of plumbers.
- Last week a company drilled a 130 meter hole for the heating system. The warm water from this hole will be connected to a heat pump, which in turn will provide warm water and floor heating.
- And end of last week the workers that built the house in December returned. They are now working on the facade, rain pipes and the roof.
Pictures of all of this, and also one of the storage space on the roof are below.
more about “What has happened the last couple of …“, posted with vodpod